while working here on the maintence crew for clairton steel mill my job was to demo a structure and clean debree after an explosin damaged a coke producing kelm.
Demo with oxy/acetlyn torch
rig and signal crane
crane set up
remove and install machinery
erected pre engineered building
installed door jams and members for overhead crane
sheeted and insulated building
worked as a connector building 12 story apartemnet complext
bolted up
installed decking
welded
bolt up point to spec
while working for roberts company i did shutdowns and industrial maintence at New bern weyhauser, grifton saw mill, roanoke rapids papermill, plymouth sawmill, and franklin va papermill
while working here we built amazon building up north. i worked as a connector and on a detail and plumb up gang on two diffrent jobs.
installed premitter cable
and did quality controll
removed pipe on nightshift to be inspected and reinstalled
did repair to log rumbler through demo onsight fab and welding
worked as a helper and installed sheeting